November 2012
Promoting and sharing of development experience and debate on
Sustainability of NDA funded projects BACKGROUND INTRODUCTION
The National Development Agency provides
grant funding to projects/programmes coupled
with capacity building in order to ensure sustain-
ability of these projects and programmes at the
function even if donor funding were not to
end of the funding contract between the NDA
and the projects. Based on this background, the
-profit organizations tend to be so reliant
The methodology that defines the roles and
funding dries up, so too do their activities.
responsibilities that the NDA plays after
approving the funds for the project until the
have its role in the NGO sector, this paper
projects, using its expertise to sustain them-
selves after the beyond the contract funding
The early warning signs of project failures
In this paper the NDA argues that besides
that can be shared so as to better mitigate
the roles of project monitoring, capacity
building and evaluations that it plays, the
institution is also best placed as a develop-
ensuring sustainability of projects; and
sustainable after the end of the funding
Next Page Sustainability of NDA funded projects | Best practice | November 2012 Methodology and outline of research From Previous section
In order to apply a useful methodology to arrive at
Social development interventions may be directed
conclusive assumptions one needs to distinguish
towards an identified social problem that requires
between income generating projects (economic de-
velopment) on the one hand and those with a more
immediate short-term relief and intervention. Once
social development emphasis. These can typically be
the social need is addressed the participants may
divided into those enterprise projects where the pri-
proceed to participate in other areas of community
mary aim of the initiative or project is to generate
income for the business. On the other hand, Early
Childhood Development (ECD), Food Security or
Capacity building projects share a common goal to
The argument is not that the NDA should not
address a particular social need identified in a tar-
examine options to strengthen the sustainability of
social development projects but rather that a
blanket approach and methodology to the different
The reason why research needs to draw this
types of NDA funded projects may achieve
distinction is because the nature of these two streams
of projects differs fundamentally. They differ in
inclusive results or worst may prove scientifically
terms of approach and the underlying methodology
flawed. Based on this background, the approach
of ECD and Food security is based on social engi-
on this paper will be dual in nature to examine
neering principles aimed at addressing a social need
what factors pose a risk to the sustainability of the
to achieve positive future outcomes with regards to
Different types of approaches
However, economic development projects are driven
by micro and macro economic fundamentals and the
There are five types of approaches required to ensure integrated reporting during the funding
objective to maximize revenue to sustain or even ex-
cycle of the project, they are:
pand the business. Therefore, the external environ-
ment that influences the project design (and imple-
Project reporting - The project implementers are
mentation) of ECD/Food security will be social fac-
required to regularly report to the NDA on
tors in nature, whereas the external factors that im-
the progress they are making against the
pact on project design for enterprises will be eco-
agreed upon activities of the project. This
includes reporting on outputs and inputs of
More importantly, because of these differences,
income generation projects normally posses the
Monitoring report by the development manag-
elements that makes it easier for such projects to
ers – As the project managers, the
sustain operations after the NDA funding ceases.
This is simply because if they don’t generate
sufficient cash flow or revenue, the business which
sponsibility to continuously monitor the
may be the source of livelihood for the participating
progress and performance of the project and
termination of a project based on its per-
formance. This is part of overall project
Continued Overleaf Sustainability of NDA funded projects | Best practice | November 2012 Performance monitoring – This is a process that is From Previous section
carried out by the Monitoring and Evaluation Unit of the
NDA. The process includes: project field visit to assess
Such a deviation must be directly linked to the long
the progress made on the project, project interviews to
term sustainability of the project – it may require a
collect primary information that explain the drivers of
new business plan to determine the viability of such
progress and the review of reports produced by the devel-
opment managers and the project staff on the status of the
Dependency is another warning sign and therefore
Mid – term evaluation – This is a process that is carried
project managers have to be really careful in main-
out by external evaluators. These evaluators are commis-
taining a healthy balance between project support,
sioned to conduct an in-depth mid-term project assessment
and creating dependence in decision making. The
on achievements of the projects against set outputs of the
NDA’s task is to project manage implementation
project. NDA funding duration is mostly between 12-36
and not to take decisions on behalf of projects. Even
months. A mid-term project evaluation report which
if project implementation goes according to plan
provides independent information on how the project is
during the NDA funding period, such initiatives
progressing. The report provides an opportunity for the
collapse immediately once the core support pillar is
project staff and Development Managers to address issues
that requires attention and also re-enforce good practice
A sign of dependence is when projects require the
Close-out evaluation – Close-out evaluations are funder’s intervention for the smallest of decisions
conducted at the end of the funding cycle of the project.
and initiative to be taken. It is also true that some
This process also uses external evaluators to conduct these
projects require a greater level of hand holding than
evaluations. The aim is to measure the impact the project
others, this then requires capacity building in the
has had on the beneficiaries , the processes used by project
form of mentoring, support, supervision as opposed
and the value for money. This information is useful for
to taking the responsibility of decision making by
lessons learned and best practice that can inform future
Some of the main challenges faced by the NDA Early warning signs of projects failure are as follows:
Write-backs of projects—these are projects
There are several challenges that the NDA faces with
that are stopped by the NDA before they are
regards to projects being able to sustain themselves after
the end of funding agreement with the project. A generic
warning sign is disfunctionality of the governance struc-
Projects starting much later than the agreed
ture of an organisation. There are examples of projects
“project start date” as per the contract. This
that the NDA has implemented where governance in the
hinders the milestones as stated in the project
Civil Society Organisation is strong, the oversight role of
plan, if the project plan is not adjusted to
the Board is normally functional and effective. In such
instances, the risk of financial mismanagement is mini-
Projects not being able to sustain themselves
mized. One can draw a direct correlation between inef-
after the NDA funds have stopped. This may
fective governance and the systematic erosion of proper
speak to the approaches and strategies used in
procedures and financial management in most projects.
the implementation of the project, which may
not have taken into account the holistic needs
A request for fundamental deviations to the original
project plan soon after the 1st tranche is paid is also an
indication of problems faced by the project, unless the
project can provide compelling evidence for the need to
Continued Overleaf Sustainability of NDA funded projects | Best practice | November 2012 From Previous Page Recommendations A Project Example: this is an example of where a late
Mentorship must be looked at as a component for effec-
start in a project went on to become a very successful
tive capacity building. Income generation projects that
project in Northern Cape, Eksteenskuil. The NDA have done well in the past can be linked to the mentor-
approved the project only in July of 2009 and the 1st
ship programme that was associated with the project.
tranche was only paid in September 2009. The project Mentorship programmes that work best are those where
involved the establishment of 18 ha of wine grapes.
the mentor is on site for a period of time. Good
You can only plant grapes in winter, however, when the
examples of this are the Tshwaraganang hydroponics
funds were paid to the project it was already too late to
and Richmond Opkomende Boere Cooperative. The
mentors in these two projects are absolute experts in
their respective fields and have established proper busi-
Moreover, the project could not be given a guarantee
ness and administrative systems at the project in addi-
that it would be approved, which means they could not
tion to transferring skills to beneficiaries.
order their plant material earlier in the year. It is normal
practice that plant material is ordered a year in advance.
Partnerships with other private institutions are also im-
portant in order to ensure that these projects are driven
However, it was then decided after the NDA paid the 1st
by a business model and have mitigation strategies for
tranche in September 2009 to wait until the following
sustainability. Partners also bring on board a range of
year to plant the wine grapes. Material such as poles
other applicable skills that may benefit the project in
and wire were ordered in so as to prevent price
escalations. Most materials were bought a year in ad-
vance but the actual project started in July 2010 when
Although it may be difficult to manage, the NDA must
ensure that specific sector departments come on board
during project implementation to provide the necessary
Although the late approval and transfer of the first
post implementation support for projects. This is
tranche proved a disaster, the situation was turned into
possibly one of the most important aspects that must be
something positive by managing the project and plan-
planned for and put in place to ensure long term sustain-
ning a year in advance with the available funds. The
risk in such conditions is normally that the project may
Revolving funds is a big issue in the NDA, but it can also be
abuse the funding while they are not actively engaged
an innovative way by the projects to become independent
in project activities. The difference in the case of and not reliant on the NDA for continuous support. It also
Eksteenskuil was that the strong governance structure
offers a counter performance strategy because beneficiaries
ensured that the entire process was a success.
must perform and not just accept it as donor funding where
there is little consequence when the project fails. It is argued
The project established 18,5 hectares of grapes in July
that projects cannot use the NDA grant funding and create a
2010. This project exports sultanas (dry grapes) to
credit scheme out of it. So, this is a continuous debate on
Europe. Wine grapes come into full production after 4
to 5 years. Some of the vines will only produce at 20% this coming harvesting season. Most of the vines should produce at least at 30 to 40 per cent in 2013/14.
However, full production of the vines is really expected to peak around 2014/15. The vines are looking good and the project is progressing well. The Cooperative decided to create a revolving fund with the NDA contribution. Each farmer who has bene-
Revolving
fitted from the wine grape project has signed a loan
agreement with the Cooperative. They will pay back the
funds….
funds to the Cooperative body once they start making money from the vines (year 5). In this way, the Coop-erative is creating a development fund which they will
Lead Author: Nthabiseng Kraai
use to empower other Cooperative members rather
Knowledge Manager: Research and Development
than relying on the NDA in future for further funding. This strategy has also forced farmers to perform since
Additional contributors: Clive Moses
they will have to pay back some of the development
Additional contributors: Nonhlanhla Koza By: Clive Moses (NDA Northern Cape provincial manager) Sustainability of NDA funded projects | Best practice | November 2012 National Development Agency 2nd Floor, Grosvenor Building 195 Jan Smuts Avenue Parktown North Tel: 011—018 5500 Sustainability of NDA funded projects | Best practice | November 2012
Pick Me Up Contemporary Graphic Art Fair at Somerset House 22 March – 1 April 2012 Pick Me Up, the UK’s first annual contemporary graphic art fair and festival, celebrating graphic arts in all its forms, returns for its biggest edition yet this spring. Open from 22 March to 1 April, the fair will showcase the very best illustrators, graphic novelists, cartoonist
HIV and Heart HealtH It’s no secret that both HIV and antiretroviral treatment can cause problems that can increase the risk of cardiovascular disease, including heart attacks and strokes. However, QUICK TIPS there are many ways to protect your heart if you’re HIV positive, including selecting antiretrovirals carefully, monitoring your lipid levels, and doing your best to control class